NEWS AND MEDIA
Company Announcements
4 November 2014
CCMC FS is completed
Lubel Coal Project Feasibility Study was completed by CCMC in the end of October, 2014. Next stage of the Project development is capital raising in accordance with updated
11 September 2014
General contractor and pre-construction activities
Based on updated in January, 2014 version of BFS general contractor of Lubelska Coal Project - China Coal Mine Construction Corp (CCMC) and Hefei project institute are developing
11 February 2014
Mine Lubelska BFS is updated
PAT «Luganskdiproshakht» elaborated an updated version of BFS for mine “Lubelska” project in January 2014.
16 July 2012
Lubelska mine project update
Based on research and calculation results of their mining consultants IMC Montan (Germany) Lubel Coal Company has revised and updated Lubeska mine project designed in 2009.
30 September 2011
Lubelska 3 exploration licence
Today Subsidiary Company CCI Lubelya has obtained special permit (license)#4061 dated 30.09.2011 for geological exploration of Lubelska 3 coal field. Total coal reserves